Flood Control and Drainage22OF0037

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BARANGAY CULIAT, QUEZON CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BARANGAY CULIAT, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱28,700,927.25. Status: Reported complete (DPWH). Contractor on record: C E M CONST INC. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Culiat, Quezon City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Quezon City 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22OF0037 Construction of Flood Control Structure,

₱28,700,927.25 · C.E. MERCADO CONSTRUCTION

4. Implementation

Contract Amount

₱28,700,927.25

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

November 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.