Construction of Flood Mitigation Structure23C00101

Construction of Aguang Flood Control Structure, Baler, Aurora

Construction of Aguang Flood Control Structure, Baler, Aurora is a DPWH-tracked public work in BALER (CAPITAL) (AURORA), AURORA, Region III. Reported contract value: ₱192,999,618.70. Status: Reported complete (DPWH). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST / 4VC BUILDERS & DEVELOPMENT CORP. Figures trace to sumbong.

BALER (CAPITAL) (AURORA), AURORA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, So. Setan, Brgy. Calabuanan, Baler, Aurora
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0022700

₱240,667.00 · FY2023

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱192,999,618.70

Progress

Reported complete (DPWH)

Start Date

July 6, 2023

Target End

September 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.