Construction of Flood Mitigation Structure23CC0382

Construction of Flood Mitigation Structure at barangay San Jose (Phase II), Calumpit, Bulacan

Construction of Flood Mitigation Structure at barangay San Jose (Phase II), Calumpit, Bulacan is a DPWH-tracked public work in CALUMPIT (BULACAN), BULACAN, Region III. Reported contract value: ₱47,022,470.19. Status: Reported complete (DPWH). Contractor on record: C E M CONST INC. Figures trace to sumbong.

CALUMPIT (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at barangay San Jose (Phase II), Calumpit, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

123 projects · ₱1.7B total · 1 flags

4. Implementation

Contract Amount

₱47,022,470.19

Progress

Reported complete (DPWH)

Start Date

April 3, 2023

Target End

November 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.