Construction of Flood Mitigation Structure23OD0139

Construction of Flood Control Wall along Sapang Alat Creek, Sta. 3+996 to 4+346, Caloocan City

Construction of Flood Control Wall along Sapang Alat Creek, Sta. 3+996 to 4+346, Caloocan City is a DPWH-tracked public work in CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region. Reported contract value: ₱93,966,981.03. Status: Reported complete (DPWH). Contractor on record: ELITE GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to sumbong.

CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region
Region: National Capital Region

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱25,000

    Probable match · score 0.91

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23OD0139 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2023-02-01 → 2024-04-16

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Flood wall / dike / revetment, cost per linear meter (flood control structure)

₱268,477 per linear m= 1.3x the National Capital Region median (n=45)

Contract cost ₱93,966,981 ÷ 350 linear m read from the DPWH title (“Sta. 3+996 to 4+346”; station range length (Sta. a+b to c+d)). National percentile: 85. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Bulacan

Based on the coordinates published with the DPWH record and NOAH file Bulacan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Construction of Flood Control Wall along Sapang Alat Creek, Sta. 3+996 to 4+346, Caloocan City

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks, Brgy. 178, Caloocan City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

121 projects · ₱7.5B total · 3 flags

Other projects by this contractor

Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱247.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱213.9M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, CANLASID SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)

Construction of Road Dike along Mag-asawang Tubig River, Sitio Dike, Barangay Apitong Section, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR

Region VIII, Region VIII

2024₱190.9M
Past target date (DPWH On-Going)
View all 121 projects →

4. Implementation

Contract Amount

₱93,966,981.03

Progress

Reported complete (DPWH)

Start Date

April 24, 2023

Target End

February 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanCity of San Jose Del MonteTungkong Mangga
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.