Construction of Revetment24CA0010

Construction of Flood Control Structure along Hermosa River (Phase III), Hermosa, Bataan

Construction of Flood Control Structure along Hermosa River (Phase III), Hermosa, Bataan is a DPWH-tracked public work in HERMOSA (BATAAN), BATAAN, Region III. Reported contract value: ₱48,999,999.92. Status: Reported complete (DPWH). Contractor on record: PASCAL CONST. Figures trace to sumbong.

HERMOSA (BATAAN), BATAAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Hermosa River ( Phase III ) , Hermosa, Bataan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000446

₱605,705.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005909

₱310,430.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007283

₱1,444,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000447

₱52,253.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005910

₱28,863.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007284

₱133,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,999.92

Progress

Reported complete (DPWH)

Start Date

February 16, 2024

Target End

August 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.