Roads19BH0055

CONCRETING OF BRGY. SAN MIGUEL - BRGY. PLANAS FMR

CONCRETING OF BRGY. SAN MIGUEL - BRGY. PLANAS FMR is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱4,975,000.00. Status: Reported complete (DPWH). Contractor on record: SHANLEY CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-BMB-B-19-0000458 · · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19BH0055 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-04-06 → 2025-08-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF BRGY. SAN MIGUEL - BRGY. PLANAS FMR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-19-0000458

₱-139,647,552.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

37 projects · ₱343.5M total · 0 flags

Other projects by this contractor

No sat.

Repair/Rehabilitation/Improvement of Flood Control and Drainage Structure Along Magat River, Bangar Section 1, Brgy. Bangar, Solano, Nueva Vizcaya

NUEVA VIZCAYA, Region II

2021₱29.7M
Reported complete (DPWH)
No sat.

Repair/Rehabilitation/Improvement of Flood Control and Drainage Structure Along Sta. Cruz River, Salinas Section 2, Brgy. Salinas, Bambang, Nueva Vizcaya

NUEVA VIZCAYA, Region II

2021₱29.7M
Reported complete (DPWH)
No sat.

Repair/Rehabilitation/Improvement of Flood Control And Drainage Structure Along Magat River, Bangar Section 2, Brgy. Bangar, Solano, Nueva Vizcaya

NUEVA VIZCAYA, Region II

2021₱29.7M
Reported complete (DPWH)
No sat.

Repair/Rehabilitation/Improvement of Flood Control and Drainage Structure Along Sta. Cruz River, Salinas Section 1, Brgy. Salinas, Bambang, Nueva Vizcaya

NUEVA VIZCAYA, Region II

2021₱29.7M
Reported complete (DPWH)
No sat.

CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ABULUG-BALLESTEROS BAY VIEW BOULEVARD INCLUDING ACCESS ROAD LEADING TO BEACH RESORTS, BALLESTEROS, CAGAYAN (PHASE 4)

Cagayan 2nd DEO, Region II

2022₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, PUROK 5,

Nueva Vizcaya DEO, Region II

2022₱14.7M
Reported complete (DPWH)
View all 37 projects →

4. Implementation

Contract Amount

₱4,975,000.00

Progress

Reported complete (DPWH)

Start Date

October 28, 2019

Target End

February 6, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region II (Cagayan Valley)IsabelaRamonPlanas
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Active faultDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.