Rehabilitation / Major Repair of Flood Control Structure21BI0048

Repair/Rehabilitation/Improvement of Flood Control and Drainage Structure Along Magat River, Bangar Section 1, Brgy. Bangar, Solano, Nueva Vizcaya

Repair/Rehabilitation/Improvement of Flood Control and Drainage Structure Along Magat River, Bangar Section 1, Brgy. Bangar, Solano, Nueva Vizcaya is a DPWH-tracked public work in NUEVA VIZCAYA, Region II. Reported contract value: ₱29,700,000.00. Status: Reported complete (DPWH). Contractor on record: SHANLEY CONST. Figures trace to sumbong.

NUEVA VIZCAYA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Repair/Rehabilitation/Improvement of Flood Control and Drainage Structure Along Magat River, Bangar Section 1, Brgy. Bangar, Solano, Nueva Vizcaya
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014076

₱272,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007842

₱50,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005356

₱5,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013813

₱3,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

37 projects · ₱343.5M total · 0 flags

4. Implementation

Contract Amount

₱29,700,000.00

Progress

Reported complete (DPWH)

Start Date

January 12, 2022

Target End

November 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.