Construction of Flood Mitigation Structure22CA0071

Construction of Flood Control Structure along Pentor, Balsik River, Balsik Section Phase ATR-1, Hermosa, Bataan

Construction of Flood Control Structure along Pentor, Balsik River, Balsik Section Phase ATR-1, Hermosa, Bataan is a DPWH-tracked public work in HERMOSA (BATAAN), BATAAN, Region III. Reported contract value: ₱39,599,984.38. Status: Reported complete (DPWH). Contractor on record: TRICHES CONST & TRADING. Figures trace to sumbong.

HERMOSA (BATAAN), BATAAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pentor, Balsik River, Balsik Section Phase ATR-1, Hermosa, Bataan á
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002954

₱303,500,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001696

₱205,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001781

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004835

₱786,019.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱39,599,984.38

Progress

Reported complete (DPWH)

Start Date

June 7, 2022

Target End

December 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.