Flood Control and Drainage21G00133

CONSTRUCTION OF SLOPE PROTECTION WORKS AND IMPROVEMENT ALONG DUNGON CREEK FROM NABITASAN BRIDGE TO BOLILAO BRIDGE, ILOILO CITY

CONSTRUCTION OF SLOPE PROTECTION WORKS AND IMPROVEMENT ALONG DUNGON CREEK FROM NABITASAN BRIDGE TO BOLILAO BRIDGE, ILOILO CITY is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱115,799,775.65. Status: Past target date (DPWH On-Going). Contractor on record: F GURREA CONST INC. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱115,799,775.65

Progress

Past target date (DPWH On-Going)

Start Date

March 17, 2022

Target End

June 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.