Flood Control and Drainage25BB0020

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM -CONSTRUCTION OF FLOOD CONTROL CABANBANAN STRUCTURE, CABANBANAN, GONZAGA, CAGAYAN

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM -CONSTRUCTION OF FLOOD CONTROL CABANBANAN STRUCTURE, CABANBANAN, GONZAGA, CAGAYAN is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱96,470,000.00. Status: Past target date (DPWH On-Going). Contractor on record: JWU CONST AND SUPPLY. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Paranan River, Baggao, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cagayan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

305 projects · ₱13.7B total · 52 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING - TERTIARY ROADS - NAGUILIAN-SAN MARIANO ROAD, ISABELA

Region II, Region II

2023₱169.0M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MIT. FACI. W/IN MAJOR BASINS & PRIN. RIVERS -CONST. OF FLOOD CONT. STRUC. ALONG ARINGAY RIVER BASIN, TUBAO, LA UNION (PACKAGE 8), TUBAO, LA UNION

La Union 2nd DEO, Region I

2025₱144.7M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRU

Isabela 2nd DEO, Region II

2024₱144.7M
Reported complete (DPWH)

Construction of Slope Protection Structure for Cagayan River Basin, Magat River, Aplat Section, Package 2, Aurora, Isabela

AURORA (ISABELA), ISABELA, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PACKAGE 2, GUIBANG,

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, TALLUNGAN

Isabela 3rd DEO, Region II

2024₱144.7M
Past target date (DPWH On-Going)
View all 305 projects →

4. Implementation

Contract Amount

₱96,470,000.00

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2025

Target End

February 26, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.