Construction of Flood Mitigation Structure23OD0035

Construction of Box Culvert at 3S Compound, Barangay Ugong, Valenzuela City

Construction of Box Culvert at 3S Compound, Barangay Ugong, Valenzuela City is a DPWH-tracked public work in CITY OF VALENZUELA (METROPOLITAN MANILA), VALENZUELA CITY, National Capital Region. Reported contract value: ₱47,937,648.46. Status: Reported complete (DPWH). Contractor on record: MRB11 CONST CORP FORMERLY:MRB CONS. Figures trace to sumbong.

CITY OF VALENZUELA (METROPOLITAN MANILA), VALENZUELA CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Pasolo-Mabolo, Brgy. Pasolo, Valenzuela City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

230 projects · ₱10.9B total · 4 flags

4. Implementation

Contract Amount

₱47,937,648.46

Progress

Reported complete (DPWH)

Start Date

February 21, 2023

Target End

January 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.