Flood Control and Drainage25CA0055

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF SABO DAM OF TANGILAD DAM AT TANGILAD SRIS, ORANI, BATAAN

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF SABO DAM OF TANGILAD DAM AT TANGILAD SRIS, ORANI, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱14,380,994.54. Status: Past target date (DPWH On-Going). Contractor on record: RSWINSLET CONST. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along San Juan River, Samal, Bataan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bataan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,380,994.54

Progress

Past target date (DPWH On-Going)

Start Date

April 8, 2025

Target End

September 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.