Flood Control and Drainage19PL0097

CONSTRUCTION OF ADDANG FLOOD CONTROL, BRGY. BALAWAG, TABUK CITY, KALINGA

CONSTRUCTION OF ADDANG FLOOD CONTROL, BRGY. BALAWAG, TABUK CITY, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱989,999.66. Status: Reported complete (DPWH). Contractor on record: JBC BUILDERS. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱989,999.66

Progress

Reported complete (DPWH)

Start Date

July 11, 2019

Target End

August 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.