GAA 2025 OO-225PI0042

CONSTRUCTION OF FLOOD CONTROL ALONG CHICO RIVER, FALIWANG-CHICO KARAYAN BRIDGE, BONTOC, MOUNTAIN PROVINCE

CONSTRUCTION OF FLOOD CONTROL ALONG CHICO RIVER, FALIWANG-CHICO KARAYAN BRIDGE, BONTOC, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱80,188,000.00. Status: Past target date (DPWH On-Going). Contractor on record: JBA CONST AND BUILDERS. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Chico River, Sitio Cheka-a, Bontoc, Mountain Province
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Mountain Province 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

67 projects · ₱929.9M total · 0 flags

Other projects by this contractor

View all 67 projects →

4. Implementation

Contract Amount

₱80,188,000.00

Progress

Past target date (DPWH On-Going)

Start Date

March 10, 2025

Target End

December 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.