Construction of Flood Mitigation Structure21HF0049

Construction of Flood Mitigation Structure at Balud River along Cebu-Toledo Wharf Rd (Uling-Toledo Wharf) K0046+400 - K0046+928, Cebu

Construction of Flood Mitigation Structure at Balud River along Cebu-Toledo Wharf Rd (Uling-Toledo Wharf) K0046+400 - K0046+928, Cebu is a DPWH-tracked public work in CEBU, Region VII. Reported contract value: ₱14,849,542.74. Status: Reported complete (DPWH). Contractor on record: O Q CONST AND SUPPLY. Figures trace to sumbong.

CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Balud River along Cebu-Toledo Wharf Rd (Uling-Toledo Wharf) K0046+400 û K0046+928, Cebu
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014167

₱122,500,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007624

₱81,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-21-0010447

₱1,265,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-21-0010448

₱109,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱14,849,542.74

Progress

Reported complete (DPWH)

Start Date

January 11, 2022

Target End

August 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.