Construction of Flood Mitigation Structure22BH0108

Construction of Flood Control along Ganano River, Sta.1 + 787 - Sta.2 + 250, Batal, Santiago City, Isabela

Construction of Flood Control along Ganano River, Sta.1 + 787 - Sta.2 + 250, Batal, Santiago City, Isabela is a DPWH-tracked public work in CITY OF SANTIAGO (ISABELA), ISABELA, Region II. Reported contract value: ₱72,374,738.52. Status: Reported complete (DPWH). Contractor on record: V B MANUBAY CONST. Figures trace to sumbong.

CITY OF SANTIAGO (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Sinsayon, Santiago City, Isabela
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002983

₱603,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001961

₱82,188,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003822

₱2,384,547.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003823

₱222,968.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱72,374,738.52

Progress

Reported complete (DPWH)

Start Date

April 12, 2022

Target End

January 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.