Construction of Flood Mitigation Structure24PJ0022

Construction of Tulaed Flood Control, Sta. 75+970 - Sta. 76+090 (L/S), Sta. 76+297 - Sta. 76+820 (L/S), Tulaed, Mayoyao, Ifugao

Construction of Tulaed Flood Control, Sta. 75+970 - Sta. 76+090 (L/S), Sta. 76+297 - Sta. 76+820 (L/S), Tulaed, Mayoyao, Ifugao is a DPWH-tracked public work in ALFONSO LISTA (POTIA) (IFUGAO), IFUGAO, Cordillera Administrative Region. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: MA CONST. Figures trace to sumbong.

ALFONSO LISTA (POTIA) (IFUGAO), IFUGAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tulaed Flood Control, Sta. 75 + 970 - Sta. 76 + 090 ( L / S ) , Sta. 76 + 297 - Sta. 76 + 820 ( L / S ) , Tulaed, Mayoyao, Ifugao
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008519

₱1,463,900.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0008532

₱135,182.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-CAR-24-0001024

₱126,419.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

49 projects · ₱715.4M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BRIDGE (UMILAG), LAMUT, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2025₱67.5M
Past target date (DPWH On-Going)
No sat.

25PJ0030: FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 40 +075- STA. 40+640, SAN JUAN, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱55.7M
Past target date (DPWH On-Going)
No sat.

23PJ0016: NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-ALFONSO LISTA-SAN MANUEL DIVERSION ROAD, IFUGAO STA. 2 +062.80-STA. 2 +514.50, STA. 5 +204.80-STA. 5+780, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱39.2M
Reported complete (DPWH)
No sat.

24PJ0004: ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS-NUEVA VIZCAYA-IFUGAO-MT PROVINCE RD-K0337+050-K0337+111, K0340+940-K0340+971, K0347+618-K0347+632, K0349+146-K0349+173

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱36.7M
Reported complete (DPWH)
No sat.

24PJ0013: ASSET PRESERVATION PROGRAM - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS-BANAUE-HUNGDUAN-BENGUET BDRY RD - K0342 + (-107), K0342 + 047, K0342 + 293, K0342 + 473 - K0342 + 570, K0342 + 885, K0343 +

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱35.6M
Reported complete (DPWH)
No sat.

24PJ0003: ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, BANAUE-MAYOYAO-A LISTA-ISABELA BDRY RD - K0341 + (-104) - K0341 + (-084), K0358 + (-034) - K0358 + 026, K0361 + 160

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱34.3M
Reported complete (DPWH)
View all 49 projects →

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

February 21, 2024

Target End

August 18, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.