Construction of Flood Mitigation Structure22PC0007

Construction of Apayao-Abulug River Basin Flood Control Structure, San Mariano Section, Sta. 24+884-Sta. 25+380 (LS), Sta. Marcela, Apayao

Construction of Apayao-Abulug River Basin Flood Control Structure, San Mariano Section, Sta. 24+884-Sta. 25+380 (LS), Sta. Marcela, Apayao is a DPWH-tracked public work in SANTA MARCELA (APAYAO), APAYAO, Cordillera Administrative Region. Reported contract value: ₱77,189,689.42. Status: Reported complete (DPWH). Contractor on record: ASC CONST & CONCRETE PRODUCTS. Figures trace to sumbong.

SANTA MARCELA (APAYAO), APAYAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cabicungan River Basin Flood Control Structure, Dappay Section, Sta. 11 + 470 - Sta. 12 + 090 (R/S), Calanasan, Apayao
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002927

₱110,759,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

21 projects · ₱1.3B total · 2 flags

4. Implementation

Contract Amount

₱77,189,689.42

Progress

Reported complete (DPWH)

Start Date

March 31, 2022

Target End

February 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.