Flood Control and Drainage18CJ0067

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG SAN BARTOLOME RIVER, NAMBALAN SECTION, MAYANTOC, TARLAC

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG SAN BARTOLOME RIVER, NAMBALAN SECTION, MAYANTOC, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱32,926,488.50. Status: Reported complete (DPWH). Contractor on record: GVDPM CONST CORP FORMERLY: ZM CONSTRUCTIO. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱35,000

    Probable match · score 0.88

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-C-18-0013294 · ₱468,675,741 · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18CJ0067 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-04-19 → 2025-02-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Tarlac

Based on the coordinates published with the DPWH record and NOAH file Tarlac.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG SAN BARTOLOME RIVER, NAMBALAN SECTION, MAYANTOC, TARLAC

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation./Improvement of Slope Protection along San Bartolome River, Nambalan Section, Mayantoc, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-18-0013294

₱468,675,741.00 · FY2018

Released to Tarlac DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

166 projects · ₱9.9B total · 2 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS - MANILA NORTH RD - K0595 + 000 - K0599 + 810; K0600 + 000 - K0600 + 979.7; K0680+000 - K0682+000; K0684+

Region II, Region II

2024₱224.7M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAPAS-BOTOLAN ROAD (BUENO BRIDGE 1), PROVINCE OF TARLAC

Region III, Region III

2021₱214.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING- PRIMARY ROADS - MANILA NORTH RD - K0601 + 074 - K0602 + 349, K0602 + 421 - K0603 + 724, K0611 + 1109 - K0612 +729

Region II, Region II

2024₱204.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING GAPS CONNECTING NR, INCLUDING ROW, CAPAS-BOTOLAN ROAD (ZAMBALES SECTION), INCLUDING ROW, ZAMBALES, PROVINCE OF ZAMBALES

Region III, Region III

2017₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES INCLUDING ROW, TO MORE THAN 2-LANES-BARANGOBONG BRIDGE-1 (BO1364LZ) ALONG PANIQUI-CAMILING-WAWA ROAD, TARLAC 1ST LEGISLATIVE DISTRICT PROVINCE OF TARLAC

Region III, Region III

2017₱165.1M
Reported complete (DPWH)
No sat.

NATIONAL ROAD AND BRIDGES-RECONSTRUCTION OF LABI BRIDGE ALONG NUEVA ECIJA-AURORA ROAD, BONGABON, NUEVA ECIJA, DAMAGED BY TYPHOON KABAYAN, LANDO AND NONA, PROVINCE OF NUEVA ECIJA

Region III, Region III

2016₱163.5M
Reported complete (DPWH)
View all 166 projects →

4. Implementation

Contract Amount

₱32,926,488.50

Progress

Reported complete (DPWH)

Start Date

February 5, 2018

Target End

July 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)TarlacMayantocNambalan
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Co-May 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.