Construction of Slope Protection Structure22CH0040

Construction/Rehabilitation of Slope Protection along Porac River, Poblacion Section, Floridablanca, Pampanga

Construction/Rehabilitation of Slope Protection along Porac River, Poblacion Section, Floridablanca, Pampanga is a DPWH-tracked public work in FLORIDABLANCA (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱48,840,963.08. Status: Reported complete (DPWH). Contractor on record: TOKWING CONST CORP FOR TOKWING CONSTRUC. Figures trace to sumbong.

FLORIDABLANCA (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Porac River, Mabical Section, Brgy. Mabical, Floridablanca, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001774

₱105,100,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002429

₱15,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006778

₱10,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003000

₱577,446,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0003758

₱1,166,734.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0003548

₱123,069.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0003759

₱109,872.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0003547

₱1,339,080.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

66 projects · ₱11.2B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF SMALL RIVER IMPOUNDING PROJECT (SRIP) ANDDRAINAGE SYSTEMS ALONG THE FOLLOWING RIVERS;A.) CADCADIR RIVER, BRGY. BACSAY CATARAOAN SUR, CLAVERIA, CAGAYANB.) CADCADIR RIVER, BRGYS. UNION AND CADCADIR, CLAVERIA, CAGAYANC.) CABICUNGAN RI

Flood Control Management Cluster, Central Office

2023₱1.4B
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION OF BANK PROTECTION WORKS ALONG CAGAYAN RIVER AT IGUIG, CAGAYAN AND AGGUNETAN, LASAM, CAGAYAN

Flood Control Management Cluster, Central Office

2019₱945.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION OF DIKE SYSTEM ALONG MADONGAN RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT

Flood Control Management Cluster, Central Office

2017₱862.9M
Reported complete (DPWH)

REHABILITATION OF DIKE SYSTEM ALONG CURA-LABUGAON RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK) LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT

Flood Control Management Cluster, Central Office

2017₱862.0M
Reported complete (DPWH)

PASIG MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, PHASE V, CONTRACT PACKAGE 6 - RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 17+450 TO STA. 18+130, LEFT AND RIGHT BANKS, MARIKINA CITY

Flood Control Management Cluster, Central Office

2017₱689.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SMALL RIVER IMPOUNDING PROJECT (SRIP) AT PAPA RIVER, BRGY. STO. NIÑO, NUEVA ERA, ILOCOS NORTE

Flood Control Management Cluster, Central Office

2019₱533.8M
Past target date (DPWH On-Going)
View all 66 projects →

4. Implementation

Contract Amount

₱48,840,963.08

Progress

Reported complete (DPWH)

Start Date

April 18, 2022

Target End

October 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.