Flood Control and Drainage20BC0021

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF RIVER CONTROL ALONG LANGGANGAN RIVER, STA. PRAXEDES, CAGAYAN

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF RIVER CONTROL ALONG LANGGANGAN RIVER, STA. PRAXEDES, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱18,796,400.00. Status: Reported complete (DPWH). Contractor on record: OCP CONST. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱19,175,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sta. Rosa Flood Control Structure along Abulug River, Abulug, Cagayan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cagayan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

196 projects · ₱1.5B total · 1 flags

4. Implementation

Contract Amount

₱18,796,400.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2020

Target End

December 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.