Municipality
Makilala
Makilala, Cotabato, Region XII (SOCCSKSARGEN). 1st income class. Population 88,522 (2024 POPCEN).
Data-quality note: 42 DPWH projects linked to Makilala have no coordinates published by DPWH, so they are not on the map and cannot be checked with satellite images.
PSGC 1204707000 · Source: PSA, PSGC 3Q 2026 Publication Datafile
Public records linked to Makilala
Counts include this municipality and every LGU under it. Each record carries how it was linked and a confidence level; figures are as recorded by the source and exclude single amounts of ₱10B+ held for verification. They are not findings.
DPWH infrastructure projects
Contracts on the DPWH Transparency portal, placed by coordinates first. Source: DPWH Transparency portal
241 records · ₱4,762,355,269.19
44 placed at Makilala level itself; the rest in LGUs under it.
- Rehabilitation of Paved Road Davao Cotabato Rd (Jct. Digos-Cotabato Sect) K1598+140-K1599+000, K1601+000-K1603+000, K1605+948-K1605+1065, K1606+205-K1606+282, K1606+539-K1607+000, K1607+825-K1609+649, K1610+000-K1610+225, K1612+700-K1614+466, K1611+₱212,827,562.96 · 2018 · medium confidence (project coordinates inside the barangay boundary)
- Road Widening of Davao-Cotabato Road (Jct. Digos-Cotabato Section), K1602+981 K1603+284 (Chainage 9818 Chainage 10134); K1603+802 K1605+980 (Chainage 10652 Chainage 12833); Makilala, North Cotabato₱172,646,838.73 · 2017 · medium confidence (project coordinates inside the barangay boundary)
- Road Widening of Davao-Cotabato Road (Jct. Digos-Cotabato Section), K1598+700 K1602+981 (Chainage 5518 Chainage 9818) Makilala, North Cotabato₱141,551,172.34 · 2017 · medium confidence (project coordinates inside the barangay boundary)
- Reconstruction of Municipal Hall in Barangay Poblacion, Makilala, Cotabato₱134,899,775.31 · 2021 · medium confidence (project coordinates inside the barangay boundary)
- Construction of Flood Control Structure Along Malasila River Package 1, Barangay Luna Sur, Makilala, Cotabato₱93,510,745.46 · 2025 · medium confidence (project coordinates inside the barangay boundary)
- Construction of Flood Control Structure Along Malasila River Package 2, Barangay Luna Norte, Makilala, Cotabato₱93,505,206.37 · 2025 · medium confidence (project coordinates inside the barangay boundary)
How linked: 197 by project coordinates inside the barangay boundary; 43 by project title names the place; 1 by project coordinates inside the city/municipality boundary.
Contracts this LGU awarded (PhilGEPS)
PhilGEPS awards where the procuring entity is this LGU. Source: PhilGEPS award notices
6 records · ₱1,273,738,035.23
1 placed at Makilala level itself; the rest in LGUs under it.
- Municipality of Makilala, North Cotabato₱1,272,219,777.65 · high confidence (the LGU itself is the buyer)
- Barangay Indangan, Makilala, Cotabato₱646,500.00 · high confidence (the LGU itself is the buyer)
- Barangay Kisante, Makilala, Cotabato₱499,372.58 · high confidence (the LGU itself is the buyer)
- Barangay Guangan - Makilala, North Cotabato₱164,500.00 · high confidence (the LGU itself is the buyer)
- Barangay New Cebu, Makilala, Cotabato₱108,985.00 · high confidence (the LGU itself is the buyer)
- Barangay New Baguio, Makilala, Cotabato₱98,900.00 · high confidence (the LGU itself is the buyer)
How linked: 6 by the LGU itself is the buyer.
PhilGEPS awards delivered here (all agencies)
Awards by any agency whose area of delivery is this province. PhilGEPS records delivery areas at province level only. Source: PhilGEPS award notices
Not yet linked to Makilala itself. This shows the province figure for Cotabato.
48,374 records · ₱127,184,702,686.36
48,313 placed at Cotabato level itself; the rest in LGUs under it.
- Cotabato₱127,184,702,686.36 · 48,313 awards · high confidence (area of delivery is this province only)
- Batangas, Bukidnon, Cagayan, Camarines Sur, Cotabato, Davao del Sur, Isabela, Pampanga, Tarlac₱112,839,000.00 · 2 awards · low confidence (area of delivery lists several provinces)
- Cebu, Compostela Valley, Cotabato, Davao del Norte₱11,470,389.68 · 1 awards · low confidence (area of delivery lists several provinces)
- Abra, Albay, Cotabato, Negros Occidental, Nueva Ecija₱9,712,257.84 · 1 awards · low confidence (area of delivery lists several provinces)
- Batangas, Bukidnon, Cagayan, Camarines Sur, Cotabato, Davao del Sur, Pampanga, Tarlac₱9,570,790.00 · 4 awards · low confidence (area of delivery lists several provinces)
- Cotabato, Metro Manila₱6,096,005.00 · 2 awards · low confidence (area of delivery lists several provinces)
How linked: 48,313 by area of delivery is this province only; 61 by area of delivery lists several provinces.
Local Government Support Fund releases
DBM LGSF project releases by province, city/municipality and barangay. Source: DBM COMPASS
19 records · ₱80,620,646.51
3 placed at Makilala level itself; the rest in LGUs under it.
- Concreting of Brgy Jose Rizal-Brgy Katipunan Ii Fmr Section₱10,000,000.00 · 2022 · high confidence (location columns in the DBM release)
- Concreting of Farm-to-Market Road₱6,606,882.17 · 2023 · high confidence (location columns in the DBM release)
- Concreting of Farm-to-Market Road₱6,606,882.17 · 2023 · high confidence (location columns in the DBM release)
- Concreting of Farm-to-Market Road₱6,606,882.17 · 2023 · high confidence (location columns in the DBM release)
- Concreting of Local Road in Barangay, Luayon, Makilala₱5,000,000.00 · 2025 · high confidence (location columns in the DBM release)
- Concreting of Farm to Market Road With Box Culvert Connecting Barangay Lura Norte to Barangay New Baguio₱5,000,000.00 · 2022 · high confidence (location columns in the DBM release)
How linked: 19 by location columns in the DBM release.
GAA budget lines naming this place
General Appropriations Act lines whose text ends in this city/municipality and province. Source: DBM General Appropriations Act
115 records · ₱2,292,862,000.00
43 placed at Makilala level itself; the rest in LGUs under it.
- Construction of Flood Control Structure Along Malasila River Package 1, Barangay Luna Sur, Makilala, Cotabato₱100,000,000.00 · 2025 · medium confidence (GAA line text names the place)
- Construction of Flood Control Structure Along Malasila River Package 2, Barangay Luna Norte, Makilala, Cotabato₱100,000,000.00 · 2025 · medium confidence (GAA line text names the place)
- Construction of Flood Control Structure Along Malasila River Package 3, Barangay Luna Norte, Makilala, Cotabato₱100,000,000.00 · 2025 · medium confidence (GAA line text names the place)
- Construction of Bridge in Santa Felomina, Makilala, North Cotabato₱55,000,000.00 · 2022 · high confidence (GAA line text names the place)
- Construction of Flood Control Dike Along Bulatukan River Package 1, Barangay Kisante, Makilala, Cotabato₱50,000,000.00 · 2025 · medium confidence (GAA line text names the place)
- Construction of Flood Control Dike Along Bulatukan River Package 3, Barangay Kisante, Makilala, Cotabato₱50,000,000.00 · 2025 · medium confidence (GAA line text names the place)
How linked: 115 by GAA line text names the place.
COA annual audit reports
Not yet linked: the COA reports loaded so far cover national agencies only. LGU audit reports are published at coa.gov.ph.
Published anomaly flags
Patterns in the linked records that reviewers checked and published. A flag is a question worth asking, not a finding of wrongdoing.
- Contractor Concentration (Flood Control)Llaban Const & Supply Formerly: Llaban ConContractor: Llaban Const & Supply Formerly: Llaban Con
- Pattern Consistent with Contract SplittingConstruction of Flood Control Dike Along Bulatukan River Sta. 63+370 - Sta. 63+710 L/S, Barangay Kisante, Makilala, CotabatoContractor: Llaban Const & Supply Formerly: Llaban Con
- Pattern Consistent with Contract SplittingConstruction of Revetment Along Malasila River, Sta. 43+980 - Sta. 44+780 L/S, Barangay Sta. Filomina, Makilala, CotabatoContractor: Llaban Const & Supply Formerly: Llaban Con
- Pattern Consistent with Contract SplittingConstruction of Flood Control Dike Along Bulatukan River, Sta. 62+270 - Sta. 62+610 R/S, Barangay New Bulatukan, Makilala, CotabatoContractor: Llaban Const & Supply Formerly: Llaban Con
- Pattern Consistent with Contract SplittingConstruction of Revetment Along Malasila River, Sta. 41+533 - Sta. 42 + 333 R/S, Barangay Sta. Filomina, Makilala, CotabatoContractor: Llaban Const & Supply Formerly: Llaban Con
- Pattern Consistent with Contract SplittingConstruction of Revetment Along Malasila River, Sta. 36+540 - Sta. 37+340 L/S, Barangay Dagupan, Makilala, CotabatoContractor: Llaban Const & Supply Formerly: Llaban Con
Contractors on linked DPWH projects
All 63 contractors on DPWH projects linked to Makilala and the LGUs under it. Click a column to sort.
Costs as recorded by DPWH; single amounts of ₱10B+ are held for verification and excluded. Flags count published automated anomalies on this contractor's projects or awards here, plus flags on the contractor itself; they are not findings.

Share this page
The card shows the public record facts and a QR code back to this page.
Barangays in Makilala (38)
- Batasan · 14 DPWH projects
- Bato
- Biangan · 1 DPWH projects
- Buena Vida · 3 DPWH projects
- Buhay · 2 DPWH projects
- Bulakanon · 13 DPWH projects
- Cabilao
- Concepcion · 4 DPWH projects
- Dagupan · 2 DPWH projects
- Garsika
- Guangan
- Indangan · 2 DPWH projects
- Jose Rizal · 1 DPWH projects
- Katipunan II · 1 DPWH projects
- Kawayanon · 3 DPWH projects
- Kisante · 26 DPWH projects
- Leboce · 2 DPWH projects
- Libertad · 2 DPWH projects
- Luayon · 1 DPWH projects
- Luna Norte · 3 DPWH projects
- Luna Sur · 4 DPWH projects
- Malabuan · 6 DPWH projects
- Malasila · 9 DPWH projects
- Malungon · 2 DPWH projects
- New Baguio
- New Bulatukan · 10 DPWH projects
- New Cebu · 2 DPWH projects
- New Israel · 3 DPWH projects
- Old Bulatukan · 5 DPWH projects
- Poblacion · 26 DPWH projects
- Rodero · 2 DPWH projects
- Saguing · 15 DPWH projects
- Santa Felomina · 6 DPWH projects
- Santo Niño · 2 DPWH projects
- San Vicente · 9 DPWH projects
- Sinkatulan · 10 DPWH projects
- Taluntalunan · 6 DPWH projects
- Villaflores
QR codes for Makilala
Print these or the flyer and post them in your barangay hall, market or school. Both use high error correction, so they still scan when partly worn.