COA flags ₱532 billion in delayed DPWH projects and ₱17 billion with visible defects. Here is what the contract records show
State auditors described delays, idle works and visible defects in the 2025 DPWH audit. We matched those headlines to completion dates, schedule indicators, workload flags and Eastern Visayas flood-control records — without inventing what satellite images cannot see.
By Love the Philippines Data Desk
Published · 10 min read · Data as of November 6, 2026

The Commission on Audit's 2025 annual audit report on the Department of Public Works and Highways (DPWH), as covered by BusinessWorld on November 3 and the Philippine Daily Inquirer on November 4, says state auditors found 9,061 infrastructure and consultancy projects worth ₱531.79 billion that were implemented inefficiently in 2025 — with delays, prolonged suspensions and idle works. Separately, COA reported that 300 projects worth ₱17.34 billion showed "visible" structural defects or discrepancies.
Those findings are about how projects were carried out and how they look on the ground. This site does not inspect concrete. What it does hold is a decade of DPWH contract records: status labels, start and target dates, completion dates, progress figures, contractor links, and, for many projects, satellite before-and-after imagery. Below we put the COA headlines next to those records — not to prove or disprove the audit, but to show what a citizen can already check in public data when auditors talk about delay, idle works and defects.
We cite the COA findings through BusinessWorld and the Inquirer. We could not open the COA PDF from this environment at publish time; if you have the Annual Audit Report, compare every quoted figure against it.
What COA reported for 2025
According to BusinessWorld's summary of the audit:
| COA observation (via BusinessWorld, Nov. 3, 2026) | Figure |
|---|---|
| Projects with inefficient implementation (delays, suspensions, idle works) | 9,061 projects · ₱531.79 billion |
| Multi-phase civil works still partially operational, idle, unusable or suspended | 50 contracts · ₱4.62 billion |
| Technical defects identified on inspection | 872 projects · ₱4.33 billion |
| Projects with visible structural defects or discrepancies | 300 projects · ₱17.34 billion |
| Advances to contractors/consultants still unrecovered from completed, terminated, rescinded, abandoned or awaiting-termination projects | ₱4.09 billion |
| Share of obligated funds disbursed by end-2025 | ₱491.72 billion of ₱1.077 trillion (45.65%) |
| Cash allocations unused and reverted to the Treasury | ₱33.67 billion |
BusinessWorld also reported that under DPWH's network development program, the agency completed 13.18 kilometers of national roads against a target of 849.71 kilometers, and 113.31 lineal meters of bridges against a target of 23,489.08 lineal meters. Auditors attributed the delivery problems to "deficiencies in project planning, detailed engineering, contract administration, supervision, monitoring and timely resolution of implementation issues."
The Inquirer focused on the defects side. It reported that COA flagged 71 projects costing ₱4.33 billion in Leyte's first district with cracks on parapet walls, missing joint sealants, minor railing corrosion and related issues; 17 projects worth ₱3.62 billion elsewhere in Eastern Visayas with cracks, damaged structural and surface components, and corrosion; and 58 projects in Tacloban City with clogged or damaged inlets and manholes, exposed steel bars and rusting railings. Auditors also noted deficient project signboards on 716 infrastructure projects. COA, as quoted by the Inquirer, said the observations "suggest weaknesses in project planning, coordination, supervision, monitoring, inspection, accomplishment validation, contract administration, warranty enforcement, and post-completion maintenance."
DPWH told both outlets it would act on the recommendations. BusinessWorld reported that the department said it would improve project preparation and monitoring, accelerate billing and strengthen settlement of audit findings. The Inquirer reported that findings had been forwarded to the offices concerned for prompt action.
None of that is a finding by this site. It is what the auditors wrote, as relayed by those newsrooms.
What our contract records show on completion and schedule
This database holds 248,550 DPWH project records (one row per contract or component after de-duplication) with a recorded cost of about ₱6,378.53 billion, of which 214,876 carry map coordinates. Status is a field DPWH (or its transparency feed) publishes on each record. As of our latest refresh:
| Recorded status | Projects | Recorded value (₱B) |
|---|---|---|
| Completed | 205,238 | 4,568.17 |
| On-Going | 34,730 | 1,766.48 |
| For Procurement | 6,800 | 0.00 |
| Terminated | 929 | 10.33 |
| Not Yet Started | 853 | 33.55 |
Most of the decade's value is marked completed. The live question for a delay story is what "On-Going" means when a target date has already passed.
Of the 34,730 on-going contracts, 34,713 (about ₱1,734.73 billion) have a target_end_date earlier than today. The median such contract is roughly 487 days past its recorded target. Only 17 on-going contracts still show a future target date. That pattern has more than one possible reading:
- many projects may be delayed or suspended, which would line up with the kind of delivery problem COA described; or
- target dates in the public feed may not be updated when schedules slip, so the field is stale even when work continues.
Both can be true in different offices. The public record alone cannot tell them apart. What it can show is how often the dates disagree with the status label.
Among completed contracts that have both an actual and a target end date:
| Outcome | Projects | Recorded value (₱B) |
|---|---|---|
| Actual end after target (completed "late" on the dates) | 52,063 | 951.34 |
| Actual end on or before target | 153,163 | 3,616.74 |
So about one in four dated completions finished after the recorded target. Again, that can mean a real delay, a revised schedule that never reached the public table, or a data-entry problem.
A sharper inconsistency: 7,911 on-going contracts (₱263.67 billion) already show progress_pct = 100 but are still labelled On-Going. A project that is 100% complete on paper and still "on-going" in status is exactly the kind of record a reader — or an auditor — would want explained.
By funding year, the on-going backlog is concentrated in recent years: 17,569 on-going 2025 contracts (₱703.77 billion) and 10,788 on-going 2024 contracts (₱564.47 billion) sit past their recorded targets, alongside older carry-overs. For 2025 overall, the status mix is 17,577 on-going, 3,691 completed, 4,174 for procurement, 699 not yet started and 2 terminated.
Flood-control and drainage contracts — the category COA's Eastern Visayas defect notes often touch — show 17,883 completed (₱628.14 billion) and 5,439 on-going (₱419.59 billion) nationwide in our records.
Eastern Visayas in the contract file
COA's defect examples, as reported by the Inquirer, clustered in Leyte's first district, wider Eastern Visayas and Tacloban. Our Region VIII (Eastern Visayas) file shows:
| Status (Region VIII) | Projects | Recorded value (₱B) |
|---|---|---|
| Completed | 5,673 | 101.85 |
| On-Going | 842 | 28.08 |
| For Procurement | 234 | 0.00 |
| Not Yet Started | 67 | 1.76 |
| Terminated | 10 | 0.07 |
Flood-control contracts in Region VIII for the two most recent funding years:
| Year | Status | Projects | Value (₱B) |
|---|---|---|---|
| 2025 | On-Going | 113 | 6.89 |
| 2025 | Completed | 8 | 0.16 |
| 2025 | For Procurement | 33 | 0.00 |
| 2024 | On-Going | 125 | 11.75 |
| 2024 | Completed | 44 | 2.65 |
| 2024 | For Procurement | 26 | 0.00 |
A large share of recent flood-control rows in the region is still marked on-going. That does not mean they are the same projects COA inspected. It does mean that anyone following the Inquirer's Leyte and Tacloban notes can open the Region VIII contract list and see how many flood-control works are still open on paper.
This article does not revisit personnel actions reported elsewhere in Surigao or Leyte. The geography here is only the geography of the audit observations.
Published schedule and workload indicators on this site
This site publishes rule-based indicators after human review. They are not COA findings. They mark patterns in the records that are worth a closer look. For delay and delivery, the most relevant published rules are:
| Rule | Title | What it looks for | Published flags |
|---|---|---|---|
| C4 | Schedule / Date Inconsistencies | Completion before start, implausibly short duration for cost, or future dates marked complete | 283 |
| C7 | High Concurrent Workload for One Contractor | One contractor linked to far more concurrent flood-control value than peers | 46 |
| C3 | Duplicate or Near-Duplicate Projects | Very similar titles at nearby locations or shared coordinates | 1,183 |
| C5 | Pattern Consistent with Contract Splitting | Clusters of similar contracts just under a ₱50 million threshold in a short window | 438 |
All 283 published C4 flags in the current set cite implausibly_short_duration — for example, a large contract whose recorded start and actual end are much closer together than peers of similar cost. Examples a reader can open:
- Slope protection along C-6 Open Channel, Phase 3, Taguig · contract 24OB0189 · recorded cost about ₱141.85 million · marked completed with an implausibly short duration relative to cost.
- Flood mitigation along Pampanga River, Palayan City, Nueva Ecija · contract 24CF0007 · about ₱69.00 million · same schedule rule.
- Flood control along Upper Marikina River, Phase VIII, Rizal · contract 24DO0081 · about ₱144.75 million.
- Flood control and drainage package along Magat-related works, Nueva Vizcaya · contract 24BI0008 · about ₱144.75 million.
C7 looks at capacity strain — many projects or very high concurrent flood-control value for one contractor versus peers. COA's delay findings often mention supervision and contract administration; a contractor carrying several times the peer 95th-percentile concurrent value is one place those pressures can show up in the award file. Published examples:
- ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP · 84 linked projects · about ₱5.74 billion total value in the flag evidence, versus a peer 95th percentile near ₱1.01 billion.
- LEGACY CONST CORP · 115 linked projects · about ₱8.29 billion in the flag evidence, same peer baseline.
High workload is an operational-risk signal. It is not proof that any single project was delayed or defective.
Duplicates and near-threshold clusters matter for a delay story because phased or fragmented packages are harder to supervise and easier to leave idle between stages — the same family of problems COA described for multi-phase works. In Eastern Visayas and nearby Surigao records, published C3 examples include:
- Salvacion Flood Control (Downstream), Albuera, Leyte · Duplicate or Near-Duplicate Projects.
- Revetment along Diit River, Phase 2, Tacloban City · Duplicate or Near-Duplicate Projects.
Nationwide, a C5 example from a flood-control cluster:
- Flood mitigation at Sapangdaku River, Cebu · Pattern Consistent with Contract Splitting · one of three near-₱50 million contracts in a short window at Cebu 3rd DEO.
District offices with the most published project-level flags on this site (all rules combined) include Bulacan 1st (176), Cebu 7th (160), Abra (101), La Union 2nd (96) and Isabela 4th (93). A high flag count means more published indicators, not a COA ranking.
Across the whole site there are 3,883 published indicators. Full rule text is on the methodology and indicators pages.
Visible defects — and what satellite records can and cannot show
COA's ₱17.34 billion "visible defects" finding is about cracks, corrosion, clogged drains, exposed steel and similar conditions seen on inspection. Our database cannot see a crack. What we do hold is project_satellite: 225,920 projects with a satellite processing row, of which 225,820 are status ok, 61 approximate_location and 39 no_clear_image. Those images can show large earthworks, channel alignment and whether a site looks disturbed between two dates. They cannot certify sealants, railing rust or inlet blockage.
So when COA reports visible defects in Leyte or Tacloban, the useful public-records move is not to claim the satellite "confirms" the audit. It is to:
- open the contract record for the office and year;
- check status, dates and progress;
- open any published schedule or duplicate indicator;
- look at satellite only as a coarse "was anything built here" check;
- read the COA observation itself for the physical defect.
Signboard gaps (716 projects in the Inquirer report) are likewise outside our automated rules. A missing billboard is a compliance and transparency issue COA raised; it does not appear as a separate flag type on this site.
Disbursement, lightly
BusinessWorld reported that DPWH disbursed only 45.65% of its ₱1.077 trillion in obligated funds by the end of 2025, and that ₱33.67 billion in cash allocations reverted unused. That cash-budgeting gap is one way delays show up in the fiscal record: money obligated but not paid out. We covered a related DBM/NCA utilization story earlier this year in DPWH left ₱59 billion in cash unused by September. Our project table's amountPaid field is not reliable enough in this refresh to restate a disbursement rate from contract rows, so we do not invent one here. The COA disbursement figures above are cited via BusinessWorld.
How to read this without accusing anyone
- COA findings are COA's. News figures above are attributed to BusinessWorld and the Inquirer summarizing the 2025 Annual Audit Report on DPWH.
- Our tables describe fields in public contract records — status, dates, progress, published indicators. They are not a judgment on any official or contractor.
- A past-target on-going row can mean delay, suspension, idle work or a stale target date. A 100% progress row still labelled on-going can mean a posting lag. An implausibly short duration can mean a data-entry error. Innocent explanations are always on the table.
- We do not name individuals as wrongdoers. We do not treat a published indicator as proof of misconduct.
- Single-record amounts of ₱10 billion or more are held for verification under our standards and are not used as headline figures here.
Right of reply
DPWH, its regional and district engineering offices, COA and any contractor named in a linked indicator page can send corrections or context through our submission page. We will update this article and note the change.
Indicator worth a closer look. Not an accusation or a finding of wrongdoing.
Related flags on this site
- Slope protection along C-6 Open Channel, Phase 3, Taguig · Schedule / Date Inconsistencies. Implausibly short recorded duration for cost.
- Flood mitigation along Pampanga River, Palayan City · Schedule / Date Inconsistencies.
- Flood control along Upper Marikina River, Phase VIII · Schedule / Date Inconsistencies.
- Flood control and drainage package, Nueva Vizcaya · Schedule / Date Inconsistencies.
- ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP · High Concurrent Workload for One Contractor.
- LEGACY CONST CORP · High Concurrent Workload for One Contractor.
- Salvacion Flood Control (Downstream), Albuera, Leyte · Duplicate or Near-Duplicate Projects.
- Revetment along Diit River, Phase 2, Tacloban City · Duplicate or Near-Duplicate Projects.
Data as of November 6, 2026 (Asia/Manila). News reports as of November 4, 2026. Contract and flag counts from the live Love the Philippines database.
Sources
- BusinessWorld: State auditors flag P532 billion in delayed, inefficient DPWH projects (Nov. 3, 2026)
- Inquirer: COA: P17-B infra works have ‘visible defects’ (Nov. 4, 2026)