Flood Control and Drainage18DK0027

CONSTRUCTION/MAINTENANE OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LALAVIÑAN RIVER, REAL, QUEZON

CONSTRUCTION/MAINTENANE OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LALAVIÑAN RIVER, REAL, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIII-18-0032863 · · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18DK0027 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-04-19 → 2017-01-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Quezon

Based on the coordinates published with the DPWH record and NOAH file Quezon.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANE OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LALAVIÑAN RIVER, REAL, QUEZON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Lalavinan River, Real, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0032863

₱0.00 · FY2018

Released to San Roque National High Ro School (Kapitangan National High School Annex-San Roque) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

831 projects · ₱32.1B total · 0 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2018

Target End

July 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)QuezonRealPandan
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Man-Yi 2024
Hazard exposure
Active faultDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.