Flood Control and Drainage24FF0042

002;CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD MITIGATION STRUCTURE,BICOL RIVER FLOOD CONTROL,BRGY. MABOLO NAGA CITY CAMARINES SUR

002;CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD MITIGATION STRUCTURE,BICOL RIVER FLOOD CONTROL,BRGY. MABOLO NAGA CITY CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱143,200,382.37. Status: Past target date (DPWH On-Going). Contractor on record: PHILWORKS CONST. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱5,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROV-24-0006883 · ₱23,392,202 · release to the district office, not itemized per project

    Possible match · score 0.68

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24FF0042 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    73% reported · imagery 2020-01-11 → 2020-01-11

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Camarines Sur

Based on the coordinates published with the DPWH record and NOAH file CamarinesSur.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: 002;CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD MITIGATION STRUCTURE,BICOL RIVER FLOOD CONTROL,BRGY. MABOLO NAGA CITY CAMARINES SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Lerma, Naga City, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0006883

₱23,392,202.00 · FY2024

Released to Camarines Sur 3rd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

81 projects · ₱6.4B total · 0 flags

Other projects by this contractor

CONSTRUCTION/IMPROVEMENT/UPGRADING OF FLOOD CONTROL ALONG SAN FRANCISCO RIVER, POLANGUI-OAS, ALBAY, POLANGUI, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2018₱281.5M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-REHABILITATION OF REVETMENT ALONG SAN FRANCISCO RIVER, UPSTREAM OF PONSO STEEL BR

Region V, Region V

2023₱280.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-PILI DIVERSION ROAD-K0450+(-348)-K0450+(-122), K0450+(-099)-K0450+772.30, K04

Region V, Region V

2024₱203.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-MABOLO-ALMEDA BYPASS RD (PACKAGE 1), CAMARINES SUR, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2023₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-REHABILITATION OF REVETMENT ALONG SAN FRANCISCO RIVER, DOWNSTREAM OF PONSO STEEL

Region V, Region V

2023₱187.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM -CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-MABOLO - ALMEDA BYPASS RD. (PACKAGE 2), CAMARINES SUR, NAGA CITY, CAMARINES SUR 3RD LEGISLATIVE DISTRICT

Region V, Region V

2023₱186.8M
Past target date (DPWH On-Going)
View all 81 projects →

4. Implementation

Contract Amount

₱143,200,382.37

Progress

Past target date (DPWH On-Going)

Start Date

April 5, 2024

Target End

March 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)Camarines SurCity of NagaTriangulo
Storms whose wind field reached it
Nokaen 2026Fung-Wong 2025Fengshen 2025Bualoi 2025Man-Yi 2024
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.