Flood Control and Drainage20PI0004

CONSTN OF FLOOD CONTROL AL CHICO RIVER, STA. 26+900-STA.27+070, MATOYTOY-OK, BONTOC ILI, BONTOC, MT PROV

CONSTN OF FLOOD CONTROL AL CHICO RIVER, STA. 26+900-STA.27+070, MATOYTOY-OK, BONTOC ILI, BONTOC, MT PROV is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱11,101,262.02. Status: Reported complete (DPWH). Contractor on record: JBA CONST AND BUILDERS 36321. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-20-0016149

₱658,571.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 36321

65 projects · ₱851.5M total · 0 flags

4. Implementation

Contract Amount

₱11,101,262.02

Progress

Reported complete (DPWH)

Start Date

February 16, 2020

Target End

July 1, 2020

5. Audit