Construction of Flood Mitigation Structure22KL0045

Construction of Flood Control Structure at Tag-anga River (Upstream of Tag-anga Bridge), Villanueva, Misamis Oriental

Construction of Flood Control Structure at Tag-anga River (Upstream of Tag-anga Bridge), Villanueva, Misamis Oriental is a DPWH-tracked public work in VILLANUEVA (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱62,725,000.00. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING & DEVELOPMENT SERVICES. Figures trace to sumbong.

VILLANUEVA (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Tagoloan River (Mohon Section), Misamis Oriental
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0008209

₱84,099.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002987

₱110,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002742

₱75,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003143

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0004831

₱47,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005264

₱1,772,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005265

₱170,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003118

₱200,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

83 projects · ₱5.7B total · 0 flags

4. Implementation

Contract Amount

₱62,725,000.00

Progress

Reported complete (DPWH)

Start Date

March 3, 2022

Target End

December 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.