Rehabilitation / Major Repair of Flood Control Structure23CE0052

Rehabilitation of Dike along Talavera River, Brgy. San Agustin, Sto. Domingo, Nueva Ecija

Rehabilitation of Dike along Talavera River, Brgy. San Agustin, Sto. Domingo, Nueva Ecija is a DPWH-tracked public work in SANTO DOMINGO (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱96,495,000.00. Status: Reported complete (DPWH). Contractor on record: AMP 723 CONST CORP FORMERLY: A M P CONST / KEVIN PAUL CONST. Figures trace to sumbong.

SANTO DOMINGO (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Talavera River, Barangay San Agustin, San Jose City, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0024916

₱371,572.00 · FY2023

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0021890

₱56,327.00 · FY2023

Released to 0000000 University of - Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,495,000.00

Progress

Reported complete (DPWH)

Start Date

February 22, 2023

Target End

November 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.