Flood Control and Drainage18OC0049

CONSTRUCTION OF BOX CULVERT ALONG DON BOSCO CREEK (FROM RUSSIA ST. TO F. SERRANO ELEMENTARY SCHOOL), BARANGAY DON BOSCO,PARAÑAQUE CITY, METRO MANILA

CONSTRUCTION OF BOX CULVERT ALONG DON BOSCO CREEK (FROM RUSSIA ST. TO F. SERRANO ELEMENTARY SCHOOL), BARANGAY DON BOSCO,PARAÑAQUE CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱27,636,000.00. Status: Reported complete (DPWH). Contractor on record: L M G CONST INC FORMERLY: LMG CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

175 projects · ₱4.0B total · 0 flags

Other projects by this contractor

View all 175 projects →

4. Implementation

Contract Amount

₱27,636,000.00

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

September 23, 2018

5. Audit