Construction of Flood Mitigation Structure23AF0112

Construction of Flood Control Structure along the Aringay River Basin, Tubao, La Union (Package 6)

Construction of Flood Control Structure along the Aringay River Basin, Tubao, La Union (Package 6) is a DPWH-tracked public work in TUBAO (LA UNION), LA UNION, Region I. Reported contract value: ₱72,334,997.36. Status: Reported complete (DPWH). Contractor on record: UNIVERSAL DE LEON CONST AND AGGREGATES. Figures trace to sumbong.

TUBAO (LA UNION), LA UNION, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along the Aringay River Basin, Tubao, La Union (Package 7)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-23-0019948

₱331,078.00 · FY2023

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

92 projects · ₱6.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱241.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG AGNO RIVER, SITIO BANAO AND SITIO ADONOT, BARANGAY AMBUKLAO, BOKOD, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2024₱147.6M
Past target date (DPWH On-Going)
No sat.

SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SAGPAT, KIBUNGAN, BENGUET TO SANTOL, LA UNION ROAD (PHASE II), KIBUNGAN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱147.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ALONG CONG. ANDRES ACOP COSALAN RD (S00379LZ) K0340+1361 - K0340+1477, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱125.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGNO RIVER MAIN STREAM (BANAO SECTION), BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱120.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ALONG CONG. ANDRES ACOP COSALAN RD (S00386LZ) K0316+375 - K0316+528, BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱120.6M
Reported complete (DPWH)
View all 92 projects →

4. Implementation

Contract Amount

₱72,334,997.36

Progress

Reported complete (DPWH)

Start Date

April 19, 2023

Target End

December 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.