Construction of Flood Mitigation Structure23CC0111

Construction of Flood Mitigation Structures along Barangay Sta. Monica, Hagonoy, Bulacan

Construction of Flood Mitigation Structures along Barangay Sta. Monica, Hagonoy, Bulacan is a DPWH-tracked public work in HAGONOY (BULACAN), BULACAN, Region III. Reported contract value: ₱77,140,881.95. Status: Reported complete (DPWH). Contractor on record: WAWAO BUILDERS. Figures trace to sumbong.

HAGONOY (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Barangay Babatnin, Malolos, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-23-0020384

₱23,856,614.00 · FY2023

Released to Division of Puerto Princesa City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

164 projects · ₱9.2B total · 15 flags

4. Implementation

Contract Amount

₱77,140,881.95

Progress

Reported complete (DPWH)

Start Date

February 13, 2023

Target End

December 9, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.