Construction of Flood Mitigation Structure23C00063

Construction of Camiling-Agno River Floodway Phase 5

Construction of Camiling-Agno River Floodway Phase 5 is a DPWH-tracked public work in CAMILING (TARLAC), TARLAC, Region III. Reported contract value: ₱193,000,000.00. Status: Reported complete (DPWH). Contractor on record: BMK CONST CORP FORMERLY B M K CONST / ROYAL CROWN MONARCH CONST & SUPPLIES CORP. Figures trace to sumbong.

CAMILING (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-23-0027032

₱10,268,343.00 · FY2023

Released to Siquijor State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱193,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 27, 2023

Target End

February 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.