Construction of Flood Mitigation Structure24CJ0276

Construction of Flood Control along Tarlac River Control Right Dike, Salapungan - Sta. Cruz Section (Segment A), Tarlac City, Tarlac

Construction of Flood Control along Tarlac River Control Right Dike, Salapungan - Sta. Cruz Section (Segment A), Tarlac City, Tarlac is a DPWH-tracked public work in CITY OF TARLAC (CAPITAL) (TARLAC), TARLAC, Region III. Reported contract value: ₱99,000,000.00. Status: Reported complete (DPWH). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to sumbong.

CITY OF TARLAC (CAPITAL) (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tarlac River - O'Donnell River Control, Balanti - Armenia Section ( Segment N ) , Tarlac City, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018106

₱90,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008257

₱1,904,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008259

₱176,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱99,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 27, 2024

Target End

October 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.