Flood Control and Drainage25OC0085

REHABILITATION OF DRAINAGE SYSTEM WITHIN ANNEX 25, BETTER LIVING SUBDIVISION, BRGY. DON BOSCO,PARAÑAQUE CITY, METRO MANILA

REHABILITATION OF DRAINAGE SYSTEM WITHIN ANNEX 25, BETTER LIVING SUBDIVISION, BRGY. DON BOSCO,PARAÑAQUE CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱14,405,440.55. Status: Past target date (DPWH On-Going). Contractor on record: P L G L CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱46,900,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure at Don Bosco Creek (Phase 2) District 2, Parañaque City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-25-0017963

₱0.00 · FY2025

Released to Regional Office - IVB (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

51 projects · ₱618.3M total · 1 flags

4. Implementation

Contract Amount

₱14,405,440.55

Progress

Past target date (DPWH On-Going)

Start Date

May 30, 2025

Target End

September 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.