Construction of Flood Mitigation Structure22DG0047

Construction of Flood Control Structure at Barangay Halang, Naic, Cavite

Construction of Flood Control Structure at Barangay Halang, Naic, Cavite is a DPWH-tracked public work in NAIC (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱33,105,536.48. Status: Reported complete (DPWH). Contractor on record: MORTAR MASTERS & CONCRETE BUILDERS. Figures trace to sumbong.

NAIC (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay Halang, Naic, Cavite
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003124

₱327,067,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002776

₱11,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002811

₱6,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱33,105,536.48

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

May 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.