Flood Control and Drainage21IA0005

CONSTRUCTION OF AMAMBAHAG FLOOD CONTROL ALONG BILIRAN CIR. ROAD (124.524397, 11.66557 TO 124.524393, 11.665548)

CONSTRUCTION OF AMAMBAHAG FLOOD CONTROL ALONG BILIRAN CIR. ROAD (124.524397, 11.66557 TO 124.524393, 11.665548) is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱19,050,500.00. Status: Reported complete (DPWH). Contractor on record: YOYEN ENT. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ungali Flood Control along Biliran Circumferential Road
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-21-0007140

₱5,039,000.00 · FY2021

Released to Home Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

72 projects · ₱1.5B total · 3 flags

Other projects by this contractor

View all 72 projects →

4. Implementation

Contract Amount

₱19,050,500.00

Progress

Reported complete (DPWH)

Start Date

February 9, 2021

Target End

July 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.