Flood Control and Drainage24DN0096

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), HALANG CREEK, BARANGAY MAYAMOT ANTIPOLO CITY (FIRST DISTRICT)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), HALANG CREEK, BARANGAY MAYAMOT ANTIPOLO CITY (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱67,549,987.05. Status: Past target date (DPWH On-Going). Contractor on record: BELL CONST. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Dalig Creek, Barangay Dalig, Antipolo City, Rizal
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Rizal 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

128 projects · ₱5.5B total · 5 flags

4. Implementation

Contract Amount

₱67,549,987.05

Progress

Past target date (DPWH On-Going)

Start Date

March 25, 2024

Target End

January 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.