Flood Control and Drainage25CJ0100

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN ISIDRO CREEK (PHASE 4), TARLAC CITY, TARLAC

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN ISIDRO CREEK (PHASE 4), TARLAC CITY, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱74,250,000.00. Status: Reported complete (DPWH). Contractor on record: CHIARA2300 INC. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Dungun Creek, Package H, Paniqui, Tarlac
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Tarlac DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱74,250,000.00

Progress

Reported complete (DPWH)

Start Date

March 18, 2025

Target End

October 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.