Flood Control and Drainage24CC0649

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAMBOG RIVER, BARANGAY MATIMBO (PUROK BAOG), MALOLOS CITY, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAMBOG RIVER, BARANGAY MATIMBO (PUROK BAOG), MALOLOS CITY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱77,199,885.93. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: SYMS CONST TRADING 48517. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱77,199,885.93

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 21, 2025

Target End

November 17, 2025

5. Audit