Flood Control and Drainage25OE0171

CONSTRUCTION OF RETARDING BASIN AT ESTERO DE MAGDALENA (PHASE III), MANILA CITY

CONSTRUCTION OF RETARDING BASIN AT ESTERO DE MAGDALENA (PHASE III), MANILA CITY is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱141,796,754.81. Status: Past target date (DPWH On-Going). Contractor on record: JIIK CONST SERVICES 50966. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Sunog Apog, Barangay 172, Manila City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

North Manila DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 50966

42 projects · ₱5.1B total · 0 flags

4. Implementation

Contract Amount

₱141,796,754.81

Progress

Past target date (DPWH On-Going)

Start Date

May 22, 2025

Target End

February 3, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.