Construction of Flood Mitigation Structure22OI0032

Construction of Flood Control Structure along Bagumbayan Creek (Muntinlupa Side) Brgy. Sucat, Muntinlupa City

Construction of Flood Control Structure along Bagumbayan Creek (Muntinlupa Side) Brgy. Sucat, Muntinlupa City is a DPWH-tracked public work in CITY OF MUNTINLUPA (METROPOLITAN MANILA), MUNTINLUPA CITY, National Capital Region. Reported contract value: ₱48,992,948.19. Status: Reported complete (DPWH). Contractor on record: L M G CONST INC FORMERLY: LMG CONST. Figures trace to sumbong.

CITY OF MUNTINLUPA (METROPOLITAN MANILA), MUNTINLUPA CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagumbayan Creek (Muntinlupa Side) Brgy. Sucat, Muntinlupa City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003114

₱1,023,303,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003031

₱10,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0006102

₱2,820,484.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0006103

₱263,928.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

175 projects · ₱4.0B total · 0 flags

Other projects by this contractor

View all 175 projects →

4. Implementation

Contract Amount

₱48,992,948.19

Progress

Reported complete (DPWH)

Start Date

February 9, 2022

Target End

April 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.