Construction of Flood Mitigation Structure22H00025

Construction of Tayud Causeway, Barangay Tayud, Sta. 0+000 - Sta. 0 + 850, Consolacion, Cebu

Construction of Tayud Causeway, Barangay Tayud, Sta. 0+000 - Sta. 0 + 850, Consolacion, Cebu is a DPWH-tracked public work in CONSOLACION (CEBU), CEBU, Region VII. Reported contract value: ₱115,799,830.60. Status: Reported complete (DPWH). Contractor on record: MORTAR MASTERS & CONCRETE BUILDERS / VSP STRUCTURE VENTURES CORP FORMERLY: VIRLO CONST. Figures trace to sumbong.

CONSOLACION (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Bakyawan, Sta. 0+000 - Sta. 1+000, Tuburan, Cebu
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003106

₱534,892,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002799

₱45,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-22-0004986

₱5,128,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-22-0004987

₱459,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱115,799,830.60

Progress

Reported complete (DPWH)

Start Date

April 8, 2022

Target End

April 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.