Construction of Flood Mitigation Structure22HE0032

Construction of Carcar River Flood Control Structure, Poblacion I, Sta. 0+000.00 - Sta. 0+504.00, Carcar City, Cebu

Construction of Carcar River Flood Control Structure, Poblacion I, Sta. 0+000.00 - Sta. 0+504.00, Carcar City, Cebu is a DPWH-tracked public work in CITY OF CARCAR (CEBU), CEBU, Region VII. Reported contract value: ₱91,674,735.35. Status: Reported complete (DPWH). Contractor on record: PRIME GIGABUILD CONST CORP FORMERLY: RON DANIELL CONST CORP. Figures trace to sumbong.

CITY OF CARCAR (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mananga River Flood Control Structure, Talisay City, Cebu
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002968

₱117,401,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱91,674,735.35

Progress

Reported complete (DPWH)

Start Date

March 25, 2022

Target End

January 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.