Construction of Flood Mitigation Structure24OA0050

Construction of Flood Control Structure, Barangay Tañong to Barangay Dampalit, Malabon City

Construction of Flood Control Structure, Barangay Tañong to Barangay Dampalit, Malabon City is a DPWH-tracked public work in CITY OF MALABON (METROPOLITAN MANILA), MALABON CITY, National Capital Region. Reported contract value: ₱93,551,903.43. Status: Reported complete (DPWH). Contractor on record: A L SALAZAR CONST INC / ROTAFLEX CONST AND DEVELOPMENT CORP FORMERLY:ROTA FLEX CONST. Figures trace to sumbong.

CITY OF MALABON (METROPOLITAN MANILA), MALABON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Dampalit Riverwall ( Phase 8 ) , Barangay Dampalit, Malabon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008740

₱1,153,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008759

₱106,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,551,903.43

Progress

Reported complete (DPWH)

Start Date

February 21, 2024

Target End

February 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.