Flood Control and Drainage25CJ0085

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER - O' DONELL RIVER CONTROL, BALANTI - ARMENIA SECTION (SEGMENT 26), TARLAC CITY, TARLAC

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER - O' DONELL RIVER CONTROL, BALANTI - ARMENIA SECTION (SEGMENT 26), TARLAC CITY, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱99,000,000.00. Status: Past target date (DPWH On-Going). Contractor on record: MOG CONST INC. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Baka River (Segment 13), Paniqui, Tarlac
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Tarlac DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

8 projects · ₱581.5M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TARLAC RIVER - O' DONELL RIVER CONTROL, BALANTI - ARMENIA SECTION (SEGMENT 27), TARLAC CITY, TARLAC

Tarlac DEO, Region III

2025₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING ALONG JCT. DAT-AN - CARMEN - SIERRA BULLONES - PILAR - ALICIA RD

Bohol 3rd DEO, Region VII

2024₱97.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - BALILIHAN-HANOPOL-BATUAN RD - K0045 + 945.50 - K0048 + 593

Bohol 3rd DEO, Region VII

2024₱83.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - LOAY INTERIOR RD - K0190+191 - K0190+276, K0193+72

Bohol 3rd DEO, Region VII

2024₱53.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, PILAR, BOHOL STA. 0+0.000.00 - STA. 2+040.0

Bohol 3rd DEO, Region VII

2024₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, GARCIA-HERNANDEZ, BOHOL SEC1: STA. 3+500.00

Bohol 3rd DEO, Region VII

2024₱49.5M
Reported complete (DPWH)
View all 8 projects →

4. Implementation

Contract Amount

₱99,000,000.00

Progress

Past target date (DPWH On-Going)

Start Date

February 24, 2025

Target End

October 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.