Rehabilitation / Major Repair of Flood Control Structure23HB0162

Rehabilitation/ Reconstruction of Napo River Control, Alicia, Bohol, Sta. 0+000 Sta. 0+500

Rehabilitation/ Reconstruction of Napo River Control, Alicia, Bohol, Sta. 0+000 Sta. 0+500 is a DPWH-tracked public work in ALICIA (BOHOL), BOHOL, Region VII. Reported contract value: ₱96,131,344.04. Status: Reported complete (DPWH). Contractor on record: KMCM BUILDERS AND DEVELOPMENT CORP / GICAR CONST INC. Figures trace to sumbong.

ALICIA (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Malitbog River Control, Dagohoy, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,131,344.04

Progress

Reported complete (DPWH)

Start Date

August 11, 2023

Target End

June 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.