Rehabilitation / Major Repair of Flood Control Structure23HB0160

Rehabilitation/Reconstruction of Manaba River Control (Phase 2), Garcia Hernandez, Bohol, Sta. 0+651.88 - Sta 0+840.00 R/S, Sta. 0+424.00 - Sta.0+866.92 L/S

Rehabilitation/Reconstruction of Manaba River Control (Phase 2), Garcia Hernandez, Bohol, Sta. 0+651.88 - Sta 0+840.00 R/S, Sta. 0+424.00 - Sta.0+866.92 L/S is a DPWH-tracked public work in GARCIA HERNANDEZ (BOHOL), BOHOL, Region VII. Reported contract value: ₱96,300,240.26. Status: Reported complete (DPWH). Contractor on record: KMCM BUILDERS AND DEVELOPMENT CORP / GICAR CONST INC. Figures trace to sumbong.

GARCIA HERNANDEZ (BOHOL), BOHOL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Cambangay River Control (LIR-Cambangay Br.), San Miguel, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,300,240.26

Progress

Reported complete (DPWH)

Start Date

August 10, 2023

Target End

June 18, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.