Flood Control and Drainage24A00425

BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BONGO RIVER, BARANGAY MEDINA, DINGRAS, ILOCOS NORTE (PHASE IV)

BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BONGO RIVER, BARANGAY MEDINA, DINGRAS, ILOCOS NORTE (PHASE IV) is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱49,499,999.13. Status: Reported complete (DPWH). Contractor on record: GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC. Figures trace to dpwh.

Region I, Region I
Region: Region I

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱48,069,041 · GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2024-02-25 → 2025-10-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Ilocos Norte

Based on the coordinates published with the DPWH record and NOAH file IlocosNorte.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BONGO RIVER, BARANGAY MEDINA, DINGRAS, ILOCOS NORTE (PHASE IV)

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24A00425

₱48,069,040.66 · GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC

Award / contract ref: 24A00425

Contractor

B

296 projects · ₱11.9B total · 3 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. ALAS-ASI-IPAG, MARIVELES, BATAAN (PACKAGE 1),

Region III, Region III

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental Mindoro

SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0078 + 722 - K0079 + 366, K0090 + 042 - K0090 + 663, K0090 + 956 - K0091 + 353

Region IV-A, Region IV-A

2024₱244.0M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Poblacion 2, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱241.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDOR

Region IV-B, Region IV-B

2024₱234.3M
Past target date (DPWH On-Going)
View all 296 projects →

4. Implementation

Contract Amount

₱49,499,999.13

Progress

Reported complete (DPWH)

Start Date

September 23, 2024

Target End

March 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)Ilocos NorteDingrasMedina
Storms whose wind field reached it
Peilou 2026Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.