Flood Control and Drainage24DI0025

REHABILITATION OF REVETMENT ALONG SAN ISIDRO RIVER, BARANGAY MAGSAYSAY, CITY OF SAN PEDRO, LAGUNA

REHABILITATION OF REVETMENT ALONG SAN ISIDRO RIVER, BARANGAY MAGSAYSAY, CITY OF SAN PEDRO, LAGUNA is a DPWH-tracked public work in Laguna 2nd DEO, Region IV-A. Reported contract value: ₱96,465,349.71. Status: Reported complete (DPWH). Contractor on record: D T RECIO INC. Figures trace to dpwh.

Laguna 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Project, Barangay Ganado, Biñan City, Laguna
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Laguna 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

43 projects · ₱5.9B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM- REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE- SECONDARY ROADS- MARINDUQUE CIRCUMFERENTIAL ROAD- K0021+500-K0021+800, MARINDUQUE

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USE'S CHANGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY STRUCTURE ALONG MINDORO WEST COASTAL ROAD, K0229+(-871)-K0263+000 (INTERMITTENT SECTIONS), OCCIDENTAL MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)

Construction of Paluan Shore Protection and Causeway Development, Sitio Ipol Section, Occidental Mindoro

PALUAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG ABRA DE ILOG RIVER, SITIO KULI-KULI SECTION (RS), ARMADO, STA. 000+234-STA. 000+900, ABRA DE IL

Region IV-B, Region IV-B

2025₱284.3M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (UPSTREAM), SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2025₱276.6M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, BUSUANGA RIVER, BRGY. SAN AGUSTIN (DOWNSTREAM), SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2025₱276.4M
Past target date (DPWH On-Going)
View all 43 projects →

4. Implementation

Contract Amount

₱96,465,349.71

Progress

Reported complete (DPWH)

Start Date

March 14, 2024

Target End

February 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.