Flood Control and Drainage18PE0003

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN, TWIN PEAKS SECTION, TUBA, BENGUET, BENGUET

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN, TWIN PEAKS SECTION, TUBA, BENGUET, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱9,071,490.10. Status: Reported complete (DPWH). Contractor on record: VALLEY CONST AND AGGREGATES. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Bued River Basin, Twinpeaks Section, Tuba, Benguet
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROX-18-0002448

₱14,611.00 · FY2018

Released to Division of Misamis Oriental (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

8 projects · ₱240.1M total · 0 flags

Other projects by this contractor

No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ACOP-KAPANGAN-KIBUNGAN-BAKUN ROAD

Benguet 2nd DEO, Cordillera Administrative Region

2017₱45.9M
Reported complete (DPWH)
No sat.

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE ALONG BENGUET-NUEVA VIZCAYA ROAD, K0298+853 - K0304+000, BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2017₱44.1M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, JCT-TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD, K0435+170-K0472+420 (S00593LZ)

Mountain Province 2nd DEO, Cordillera Administrative Region

2018₱37.5M
Reported complete (DPWH)
No sat.

ND - OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE ALONG GUREL-BOKOD-KABAYAN-BUGUIAS-ABATAN RD, K0343 + -746 - K0343 + 511, K0344 + 117 - K0344 + 203, K0344 + 228 - K0345 + 534, K0345 + 570 - K0346 + 604

Benguet 2nd DEO, Cordillera Administrative Region

2017₱34.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, IMPROVEMENT OF KALIMBATAWA CIRCUMFERENTIAL ROAD AND DRAINAGES AT SITIO KALIMBATAWA, OTUCAN SUR, STA. 0+

Mountain Province 1st DEO, Cordillera Administrative Region

2018₱25.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, NACAWANG-MABALITE ROAD CONNECTING BARANGAYS BATAYAN AND MABALITE IN SUPPORT TO SUGARCANE, COFFEE, MANGO AND FURNITURE INDUSTRIES, TADIAN, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2018₱23.8M
Reported complete (DPWH)
View all 8 projects →

4. Implementation

Contract Amount

₱9,071,490.10

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

May 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.